VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Dec. 23 – 29, 2018

VDOT will suspend most highway work zones and lift most lane closures on interstates and other major roads in Virginia from noon Monday, Dec. 24, until noon Wednesday, Dec. 26.
All work is scheduled weather permitting.  Real-time information on work zones and lane closures is available on 511Virginia. For more information about an individual project, you can either click the project title links below or visit the project page at http://www.VirginiaDOT.org
Interstate 95 Southbound
(Update)Wednesday – Friday, 9 p.m. – 10 a.m., Expect a single lane closure between mile marker 129 which is near Exit 130 (Route 3) and Exit 136 (Centreport Parkway).
Route 17 Southbound
·      Wednesday, 12 p.m. – 3 p.m. and7 p.m. – 3 p.m. Thursday
·      Thursday, 8 a.m. – 3 p.m. and 7 p.m. – 12 a.m. Friday
·      Friday, 10 p.m. – 9 a.m. Saturday
Expect a single right lane to be closed on Route 17 southbound between Sanford Drive and Short Street.
Route 17 Northbound (24-hour closure)
Starting Wednesday, Dec. 26 at 12 p.m., be alert to the 24-hour closure of a single right lane on Route 17 northbound between Sanford Drive and Short Street for construction activities related to the project. The 24-hour closure is needed to allow crews to work safely with construction equipment near the on- and off-ramps, travel lanes and underneath the I-95 overpasses.
Courthouse Road Widening Work:
Monday, 9 a.m. –12 p.m., Wednesday, 12 p.m. – 2:30 p.m., Thursday, 9 a.m. – 2:30 p.m.and Friday, 9 a.m. – 12 p.m. Expect brief delays with alternating, one-way traffic at the following locations:
  • Courthouse Road between Austin Ridge Drive and Mine Road, Cedar Lane to Walpole Street and Austin Ridge Drive to Red Oak Drive.
  • Ramoth Church Road
  • Snowbird Lane
  • Winding Creek Road
  • Woodcutters Road
  • Wyche Road
A flagging crew will direct drivers in each work zone.
Spotsylvania County Work Zones
Route 620 (Harrison Road)
(New) Thursday – Friday, 9 a.m. – 4 p.m. Expect alternating lane closures on Route 620 (Harrison Road) between Old Plank Road and Gordon Road to allow crews to take soil samples.
King William County Work Zone
Route 30
Wednesday, 12 p.m. – 4 p.m. and Thursday − Friday, 9 a.m. – 4 p.m. Expect alternating lane closures on Route 30 in King William County near the Caroline County line to allow crews to install center line rumble strips. Expect brief delays at various locations with the mobile operation.
Other Fredericksburg District Projects
Stafford County
·       Route 608 (Brooke Road) CLOSED for Stafford County Project
Brooke Road is closed near Eskimo Hill Road. This is a Stafford County project to realign the roadway to improve safety and drainage. The road will remain closed until February 2019. For more information about the project and the detour route, please visit the county’s project page.
Spotsylvania County
·      Route 658 (Mount Olive Road) Bridge Replacement – Road CLOSED
Other Fredericksburg District Projects
Stafford County
·       Route 608 (Brooke Road) CLOSED for Stafford County Project
Brooke Road is closed near Eskimo Hill Road. This is a Stafford County project to realign the roadway to improve safety and drainage. The road will remain closed until January 2019. For more information about the project and the detour route, please visit the county’s project page.
Spotsylvania County
·      Route 658 (Mount Olive Road) Bridge Replacement – Road CLOSED

2 comments

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.